Notice of the China (Shanghai) Pilot Free Trade Zone on the Examination and Approval of the Completion Acceptance of Construction Project Environmental Protection Facilities
The English version is for reference only. If there is any inconsistency or conflict between the English and Chinese version, the Chinese version shall prevail.
I. Operation Basis
Environmental Protection Law of the People’s Republic of China, Regulations on the Administration of Construction Project Environmental Protection, Regulations of Shanghai on Environmental Protection, and Measures of Shanghai on Implementation of the Law of the People’s Republic of China on Evaluation of Environmental Effects
II. Scope of Application
Construction projects in the district
III. Required Materials
1. Report on application for final acceptance of environmental protection facilities of construction projects (format text, in quintuplicate)
2. Report on environmental monitoring (original, in duplicate)
3. Reply for evaluation of environmental effects of construction projects (photocopy, in duplicate)
4. Reply for pilot production of construction projects(photocopy, in duplicate)
For Yangshan and Airport areas, the following shall also be provided:
5. Business License or Legal Person Certificate; if the applicant is an individual, the personal ID certificate shall be provided
6. Drainage License
IV. Handling Procedures
1. The applicant shall, before expiration of the pilot production (trial running), declare and report materials to the administration license acceptance window of Shanghai Free Trade Zone Management Committee.
2. Review by Shanghai Free Trade Zone Management Committee
3. Issuance of acceptance inspection opinion by Shanghai Free Trade Zone Management Committee
If the construction projects fail to reach the acceptance inspection requirements for production load upon expiration of the pilot production (trial running), after consent of the environmental protection department reviewing the documents relating to evaluation of environmental effects, final acceptance of the environmental protection facilities may be conducted according to the actual production load. After the project production reaches the specified load, it may apply for formal acceptance inspection
V. Handling Deadline
Decision shall be made within 10 working days from the acceptance day.
VI. Application Location and Contact Information
Room 1707, No. 9 Jilong Road, Pudong New Area, Shanghai
Post Code: 200131
Contacts: Wu Wei and Sun Yue
Contact Tel.: 021-58698715(WaiGaoQiao), 021-58696827 (Airport and Yangshan)
Fax: +86-21-58698720
VII. Complaint Mode
Mode of Complaint to the Management Committee of the China (Shanghai) Pilot Free Trade Zone
Tel.: +86-21-58697800
Fax: +86-21-58698705
E-mail: ftzts@pudong.gov.cn
Provided by Lawyers Working Committee of Pudong New Area