tel

Home > Environmental Protection Examination Approval

Notice of the China (Shanghai) Pilot Free Trade Zone on the Examination and Approval of the Completion Acceptance of Construction Project Environmental Protection Facilities

en.china-shftz.gov.cn Updated: 2022-08-18

The English version is for reference only. If there is any inconsistency or conflict between the English and Chinese version, the Chinese version shall prevail.

I. Operation Basis

Environmental Protection Law of the People’s Republic of China, Regulations on the Administration of Construction Project Environmental Protection, Regulations of Shanghai on Environmental Protection, and Measures of Shanghai on Implementation of the Law of the People’s Republic of China on Evaluation of Environmental Effects

II. Scope of Application

Construction projects in the district

III. Required Materials

1. Report on application for final acceptance of environmental protection facilities of construction projects (format text, in quintuplicate)

2. Report on environmental monitoring (original, in duplicate)

3. Reply for evaluation of environmental effects of construction projects (photocopy, in duplicate)

4. Reply for pilot production of construction projects(photocopy, in duplicate)

For Yangshan and Airport areas, the following shall also be provided:

5. Business License or Legal Person Certificate; if the applicant is an individual, the personal ID certificate shall be provided

6. Drainage License

IV. Handling Procedures

1. The applicant shall, before expiration of the pilot production (trial running), declare and report materials to the administration license acceptance window of Shanghai Free Trade Zone Management Committee.

2. Review by Shanghai Free Trade Zone Management Committee

3. Issuance of acceptance inspection opinion by Shanghai Free Trade Zone Management Committee

If the construction projects fail to reach the acceptance inspection requirements for production load upon expiration of the pilot production (trial running), after consent of the environmental protection department reviewing the documents relating to evaluation of environmental effects, final acceptance of the environmental protection facilities may be conducted according to the actual production load. After the project production reaches the specified load, it may apply for formal acceptance inspection

V. Handling Deadline

    Decision shall be made within 10 working days from the acceptance day.

VI. Application Location and Contact Information

Room 1707, No. 9 Jilong Road, Pudong New Area, Shanghai

Post Code: 200131

Contacts: Wu Wei and Sun Yue

Contact Tel.: 021-58698715(WaiGaoQiao), 021-58696827 (Airport and Yangshan)

Fax: +86-21-58698720

VII. Complaint Mode

Mode of Complaint to the Management Committee of the China (Shanghai) Pilot Free Trade Zone

Tel.: +86-21-58697800

Fax: +86-21-58698705

E-mail: ftzts@pudong.gov.cn

Provided by Lawyers Working Committee of Pudong New Area